WORK PROGRESS

On-line

broadcasting

SEPTEMBER-NOVEMBER’ 24

• Concreting of ground floor and first floor slabs.
• Concreting of walls and pillars on the ground floor and first floor.
• Start of laying electrical wiring and lighting of the parking floors.

SEPTEMBER-NOVEMBER’ 24

JUNE-AUGUST’ 24

• Completion of the foundation slab.
• Concreting of basement walls and pillars -1.
• Concreting of the basement slab.
• Concreting of perimeter walls and interior pillars of semi-basement floor.

JUNE-AUGUST’ 24

MAY 24

• Untensioning of provisional ground stabilization anchors (first row of south zone).
• Concreting of walls and pillars in basement -1 (south zone).
• Positioning of the tower crane.
• Concreting of the foundation slab in the northern part of the plot.
• Placement of reinforcement and formwork for walls and pillars in basement -1 (north zone).

MAY 24

APRIL' 24

• Concreting of the foundation slab in the southern area of the plot.
• Laying of the waterproof sheeting, reinforcement and drainage installations of the foundation slab in the northern area of the plot.
• Execution of elevator shafts and rainwater tank in the foundation slab.

APRIL' 24

MARCH' 24

• Preparation works of the excavation base for the execution of the foundation slab.
• Placement of the waterproofing sheet under the foundation slab.
• Placement of the safety grounding system under the foundation slab.
• Drying and channeling of the plot water from the water table.

MARCH' 24

DECEMBER' 23 - FEBRUARY' 24

• Execution of the second row of anchors on the perimeter of the entire construction site.
• Excavation of the plot until reaching the third excavation platform for the execution of the ground support anchors.
• Execution of the third row of anchors on the perimeter of the entire construction site.
• Excavation of the plot up to the bottom of the excavation for the execution of the foundation slab.
• Drying of the plot water from the water table.

DECEMBER' 23 - FEBRUARY' 24

NOVEMBER' 23

• Excavation of the plot until reaching the second platform for the execution of the ground support anchors.

• Execution of the second row of anchorages in the east and west area of the plot.

NOVEMBER' 23

AUGUST-
OCTUBRE '23

• Completion of screen walls.
• Excavation of the plot until reaching the second platform for the execution of the ground support anchors.
• Execution of the first row of anchors in the western area of the plot.
• Preparation of the second row of anchors on the west and east side of the plot.

AUGUST-
OCTUBRE '23

JULY ‘23

• Execution of 24 diaphragm walls. There are 37 screens executed out of a total of 52.

• The plot has begun to be excavated up to the first excavation level for the execution of the first row of anchors for the diaphragm walls.

JULY ‘23

JUNE '23

- Placement of tarpaulin to protect neighboring party walls.

- Placement of movement control targets in neighboring buildings.

- Painting of perimetral tanca of work of black color.

- Construction of 13 diaphragm walls out of a total of 52.

JUNE '23

May '23

Status of the work month of May Clearing and conditioning of the plot.

Placement of the perimeter fence with acoustic tarpaulin.

Placement of the construction shed and dressing room.

Construction of a guide wall for the construction of diaphragm walls (excavation).

Execution of the groundwater and connection to the AFS (sanitary cold water) network.

May '23