• Execution of the second row of anchors on the perimeter of the entire construction site.

• Excavation of the plot until reaching the third excavation platform for the execution of the ground support anchors.

• Execution of the third row of anchors on the perimeter of the entire construction site.

• Excavation of the plot up to the bottom of the excavation for the execution of the foundation slab.

• Drying of the plot water from the water table.

en_USEnglish